MRP improves planning when information about required manufacturing materials and quantities is insufficient or incorrect. Material Requirements Planning uses the production schedule, bill of materials, inventory records, lead times, and existing orders to calculate what components are needed, how many are needed, and when they should be ordered or produced.
Answer (b)
Why not others:
- (a) drawing versions and design-change history are better addressed by document, CAD, or product-lifecycle management
- (c) controlling and approving excessive design-change requests is an engineering change-management issue
- (d) MRP plans material needs but does not directly solve rising capital cost for flexible production equipment
Key rule: MRP answers three material questions: what is required, how much is required, and when it is required.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.