ITPEC IP April 2019 Question 86

Source exam: ITPEC IP April 2019Topic: Business Industry

ITPEC IP April 2019 — Question 86 of 100

MRP improves planning when complex product structures make required material quantities and order quantities difficult to calculate. It uses the production schedule, bills of materials, inventory records, and lead times to determine what components are needed, how many, and when.

Answer (b)

Why not others:
- drawing versions and change histories are managed by document, CAD, or product-data systems

- frequent design changes are not solved merely by calculating material requirements

- the cost of production equipment is a capacity and investment issue

Key rule: MRP converts planned production into time-phased component purchase and production requirements.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.