MRP improves a situation where required-material and quantity information is insufficient or incorrect. It uses the master production schedule, bill of materials, inventory records, and lead times to calculate what materials are required, how many are needed, and when orders should be released.

Answer (b)

Why not others:
- drawing versions and design histories are managed by PDM or document management

- excessive design-change requests require design or change-process improvement

- production-equipment cost for high-mix work is not solved by material requirements calculation

Key rule: MRP converts planned production into time-phased dependent demand for components and materials.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.