ITPEC IP April 2024 Question 54
ITPEC IP April 2024 — Question 54 of 100
The project manager should assess the requested function's impact and process it through formal change management. A scope change can affect cost, schedule, quality, resources, risks, contracts, and existing deliverables. The request should be documented, analyzed, and submitted to the authorized decision makers before any baseline is changed or implementation begins.
Answer (c)
Why not others:
- (a) acceptance and resource commitment before analysis bypass controlled approval
- (b) a late request is not automatically rejected; its value and impact must be evaluated
- (d) scope rarely changes in isolation, and a baseline must not be updated before the change is approved
Key rule: Evaluate first, approve or reject through the defined authority, and only then update affected baselines and execute the approved change.
AI-generated — may contain errors