ITPEC IP April 2020 Question 55
ITPEC IP April 2020 — Question 55 of 100
Evaluation standards should be prepared before selecting the supplier of a product or service. Predetermined criteria and weights allow proposals to be compared consistently on factors such as functionality, quality, cost, schedule, capability, and risk.
Answer (c)
Why not others:
- a communication plan defines how project information will be exchanged
- test cases verify a delivered product
- a project charter formally authorizes a project
- none provides the direct basis for fair vendor selection
Key rule: Establish objective procurement evaluation criteria before reviewing bids to ensure transparent and consistent selection.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.