System Planning
14 questions · Fundamental Engineering
When an information system is procured through the steps shown in the figure below, which of the following is a word or phrase that should be inserted in the blank B?
The orderer indicates the purpose of the systemization and the details of the business to a vendor, and requests provision of information.
The orderer indicates the system that is the target of the procurement and conditions of the procurement to a vendor, and requests submission of a proposal document.
The orderer determines a procurement source on the basis of the proposal document and capabilities of the vendor.
The orderer and the procurement source mutually confirm their roles and the assignment of responsibilities on a document.
Which of the following is an appropriate feasibility evaluation when checking whether the lifetime benefits of the proposed information system are greater than its lifetime costs?
Which of the following is the work that is performed when non-functional requirements are defined?
The RFP is presented to each vendor that has responded to an RFI. Which of the following should be done beforehand to proceed fairly with the future vendor selection processes?
Procurement is performed by using the comprehensive evaluation bidding method under the conditions shown below. When the bidding prices and technology points of Companies A to D are as shown in the table below, which of the following is the successful bidder?
[Conditions]
[Bidding price and technology points of Companies A to D]
Which of the following is an explanation of green procurement (sustainable procurement)?
In computerization planning, which of the following is an activity that should be performed?
In computerization investment planning, which of the following is an explanation of ROI as an evaluation index for investment value?
In the verification of stakeholder requirements, which of the following indicates the ability to keep track of the process until the implementation of a change request?
Which of the following is an activity that is performed when non-functional requirements are defined?
Which of the following is an explanation of the non-functional requirements definition?
A company chooses products and services that are acknowledged as actively addressing environmental concerns. What is this initiative called?