ITPEC FE Morning October 2022 Question 64
In computerization planning, which of the following is an activity that should be performed?
Explanation
Assigning roles between the business and information-system departments and setting the basis for costs — both are decided when the system is planned, before any design.
Computerization (systemization) planning sets the frame for a development: its scope and schedule, the organization that will build it (what the business departments and the information-system department each do), and the expected costs of development, operation and maintenance, with how they are calculated. Every later process works inside that frame.
Answer (a)
Why not others:
- •(b) — designing screens and forms from the requirements definition document is system design, which comes after requirements definition
- •(c) — keeping the system fit for the business and analysing the impact of modification requests is maintenance
- •(d) — planned startup, shutdown, monitoring and file maintenance, with checks that the business runs smoothly, is operation
Key rule: Planning fixes who does the work and how costs are counted; design decides what the system looks like; operation and maintenance keep it running and fit after release.
System Planning · AI-written, may contain errors
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.