Procurement is performed by using the comprehensive evaluation bidding method under the conditions shown below. When the bidding prices and technology points of Companies A to D are as shown in the table below, which of the following is the successful bidder?
[Conditions]
[Bidding price and technology points of Companies A to D]
Explanation
Company C, with 90 points — once the bid above the target price is excluded, C has the highest sum of price points and technology points.
Company D bids 110 thousand dollars, above the 100,000-dollar target price, so it is not evaluated. For the others, price points are 100 × (1 − bidding price ÷ target price):
Answer (c)
Why not others:
- •(a) Company A — the cheapest bid earns the most price points, 30, but its 50 technology points leave it at 80
- •(b) Company B — 20 + 65 = 85, still 5 points short of C
- •(d) Company D — its bid exceeds the target price, so it is not evaluated at all; even if it were, its price points would be (1 − 1.1) × 100 = −10 and its total of 90 would only tie C
Key rule: In comprehensive evaluation bidding, first discard bids above the target price, then rank by price points plus technology points, not by price or technology alone.