ITPEC FE Subject A April 2024 Question 48

Source exam: ITPEC FE Subject A April 2024Topic: System Strategy

ITPEC FE Subject A April 2024 — Question 48 of 60

The procurement sequence is: RFI → RFP → RFQ

  • RFI (Request for Information) — collect general info from vendors
  • RFP (Request for Proposal) — request specific system proposals against defined requirements
  • RFQ (Request for Quotation) — request pricing for a defined scope

Why not others:
- (a) — describes a system requirements specification, not an RFI

- (b) — RFI is created before an RFP, not after

- (c) — describes an RFP, which requests specific implementation proposals

Key rule: RFI = "Information" — you're just asking vendors what they can do, with no specific requirements yet.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.