ITPEC FE Subject A April 2024 Question 48

Which of the following is an appropriate description of an RFI?

Explanation

A request for information on computerization from prospective suppliers — an RFI gathers information from vendors before the requirements are fixed.

Procurement runs in this order:

  • •RFI (request for information): ask vendors what technologies, products and track record are available
  • •RFP (request for proposal): present the fixed requirements and ask for concrete system proposals
  • •Evaluate the proposals and select a supplier

What the RFI brings back helps the orderer write the RFP.

Answer (d)

Why not others:

  • •(a) — a document that already fixes the system's purpose, functions, requirements and contract matters sets out requirements, the content sent with an RFP; an RFI comes earlier and fixes none of them
  • •(b) — reverses the order: the RFI comes before the RFP and feeds into it
  • •(c) — requesting specific system proposals from vendors is an RFP

Key rule: An RFI asks vendors what they can offer; an RFP asks them to propose a system for stated requirements, so information always comes before proposals.