ITPEC FE Morning October 2020 Question 53

Source exam: ITPEC FE Morning October 2020Topic: Project Management

ITPEC FE Morning October 2020 — Question 53 of 80

Given: 500 FP, productivity = 10 FP/person-month, installation & education = 10 person-months, project management = 10% of (development + installation + education).

  • Development: 500 ÷ 10 = 50 person-months
  • Installation & education: 10 person-months
  • Subtotal: 50 + 10 = 60 person-months
  • Project management: 60 × 0.1 = 6 person-months
  • Total: `60 + 6 = 66` person-months

Why not others:
- (a) 51 — applies management to development only and omits installation/education

- (b) 60 — omits project management entirely

- (c) 65 — applies management (10%) to development only, not to the full subtotal

Key rule: Project management overhead is calculated on the combined effort of all non-management activities (development + installation + education), not just development alone.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.