Given: 500 FP, productivity = 10 FP/person-month, installation & education = 10 person-months, project management = 10% of (development + installation + education).
- •Development:
500 ÷ 10 = 50person-months - •Installation & education:
10person-months - •Subtotal:
50 + 10 = 60person-months - •Project management:
60 × 0.1 = 6person-months - •Total: `60 + 6 = 66` person-months
Why not others:
- (a) 51 — applies management to development only and omits installation/education
- (b) 60 — omits project management entirely
- (c) 65 — applies management (10%) to development only, not to the full subtotal
Key rule: Project management overhead is calculated on the combined effort of all non-management activities (development + installation + education), not just development alone.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.