ITPEC FE Morning October 2019 Question 54

Source exam: ITPEC FE Morning October 2019Topic: Project Management

ITPEC FE Morning October 2019 — Question 54 of 80

Critical Path Method — find the longest path through a project network to determine minimum project duration.

Calculate the total duration of every path from start to finish:

  • (a) A→B→E→I→L = 2+3+1+2+3 = 11
  • (b) A→C→D→E→H→K = 2+3+1+1+3+2 = 12
  • (c) A→C→F→I→L = 2+3+3+2+3 = 13
  • (d) A→C→G→J→L = 2+3+4+2+3 = 14 (longest)

The critical path is (d) A→C→G→J→L with a total duration of 14 days.

Why not others:
- (a) A→B→E→I→L = 11 days, 3 days shorter

- (b) A→C→D→E→H→K = 12 days, 2 days shorter

- (c) A→C→F→I→L = 13 days, 1 day shorter

Key rule: The critical path is the longest path from start to finish — any delay on it delays the entire project. Always check all paths before choosing.

AI-generated — may contain errors