ITPEC FE Morning April 2020 Question 53

Source exam: ITPEC FE Morning April 2020Topic: Project Management

ITPEC FE Morning April 2020 — Question 53 of 80

The critical path is the longest path through the network, determining the minimum project duration.

Calculate each path's total duration:

  • (a) A→B→E→I→L: 2+3+1+2+3 = 11 days
  • (b) A→C→D→E→H→K: 2+3+1+1+3+2 = 12 days
  • (c) A→C→F→I→L: 2+3+3+2+3 = 13 days
  • (d) A→C→G→J→L: 2+3+4+2+3 = 14 days

Why not others:
- (a) 11 days — shortest path, plenty of slack

- (b) 12 days — not the longest

- (c) 13 days — close but 1 day shorter than (d)

Key rule: The critical path is the longest path from start to finish — any delay on it delays the entire project.

AI-generated — may contain errors