Requirements definition process — this process clarifies required system functions and obtains stakeholder agreement.

Starting from the computerization plan, analysts elicit user and stakeholder needs, resolve conflicts, define functional and nonfunctional requirements, and confirm a shared baseline. Development then designs and builds against those agreed requirements.

Answer (b)

Why not others:
- (a) establishes the computerization concept, objectives, scope, and overall plan

- (c) designs, implements, and tests the solution

- (d) deploys, runs, monitors, and supports the system in use

Key rule: Planning decides why and broadly what to pursue; requirements definition makes needed behavior and quality explicit before development.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.