In the PDCA cycle of service level management, which of the following is implemented as C (Check)?

Explanation

Monitoring and measuring the services and preparing a service report — in the PDCA cycle of service level management, Check measures what was actually delivered.

Service level management runs its own PDCA cycle around the SLA:

  • •Plan — agree the desired service quality with the customer from the service requirements and the improvement plan, and document it as an SLA
  • •Do — provide the services according to the SLA
  • •Check — monitor and measure the services provided, compare them with the SLA targets, and prepare a service report
  • •Act — review the service report with the customer and prepare a service improvement plan, which feeds the next Plan

Answer (d)

Why not others:

  • •(a) — providing the services on the basis of the SLA is Do
  • •(b) — preparing a service improvement plan on the basis of the service report and its review results is Act
  • •(c) — agreeing on the service quality and preparing the SLA is Plan

Key rule: In service level management the SLA is the Plan and the service report is the Check; the report is what the Act review works from.