ITPEC IP April 2022 Question 56
ITPEC IP April 2022 — Question 56 of 100
The project manager should assess the cost and schedule impact and process the request through formal change management. A new function changes project scope and may also affect time, cost, quality, resources, risks, and contractual commitments. The authorized decision-makers need this impact analysis before approving or rejecting the change and updating any baseline.
Answer (c)
Why not others:
- (a) accepts the request before it is evaluated and approved
- (b) rejects it solely because of timing rather than business value and impact
- (d) assumes only scope is affected and changes the baseline without authorization
Key rule: Requested changes are documented, impact-analyzed, approved or rejected through change control, and only then reflected in project baselines.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.