Stakeholders are individuals or organizations that affect, are affected by, or perceive themselves to be affected by a project. They include users, sponsors, managers, project members, suppliers, regulators, and other interested parties.

Answer (a)

Why not others:
- sponsors are only one stakeholder category

- positive and negative uncertain events are risks

- deliverables and the tasks that create them describe project scope or WBS content

Key rule: Stakeholder is the broad people-and-organizations concept, not merely sponsors, risks, or work products.