ITPEC IP April 2019 Question 52

Source exam: ITPEC IP April 2019Topic: Project Management

ITPEC IP April 2019 — Question 52 of 100

Stakeholders are individuals or organizations that affect, are affected by, or perceive themselves to be affected by the project. Users and development managers are examples, and the full group can also include sponsors, customers, suppliers, regulators, and team members.

Answer (a)

Why not others:
- sponsors are only one category of stakeholder

- events with positive or negative effects are project risks

- deliverables and the tasks that create them describe project scope or a work breakdown structure

Key rule: A stakeholder is a person, group, or organization with an interest in or influence on the project or its outcome.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.