ITPEC IP April 2022 Question 51

Source exam: ITPEC IP April 2022Topic: Project Management

ITPEC IP April 2022 — Question 51 of 100

Project quality management defines and controls the procedures and performance measures needed to satisfy deliverable acceptance criteria. It plans quality standards, assures that suitable processes are followed, and checks results so deliverables meet the required level of quality.

Answer (a)

Why not others:
- (b) is project cost management, which plans and controls spending against the budget

- (c) is project risk management, which identifies, analyzes, responds to, and monitors uncertainty

- (d) is project scope management, which defines and controls the work required for project success

Key rule: Quality management focuses on standards, processes, measurements, and acceptance; cost, risk, and scope have their own management areas.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.