ITPEC IP April 2022 Question 52

Source exam: ITPEC IP April 2022Topic: Project Management

ITPEC IP April 2022 — Question 52 of 100

The whole project is delayed by one day. The original path durations are A–D = 2 + 4 = 6 days, B–E = 4 + 3 = 7 days, and C–F = 7 + 1 = 8 days, so C–F is initially the critical path. A and D are delayed by three days in total, making their path 6 + 3 = 9 days. The project duration therefore changes from 8 to 9 days, a delay of one day.

Answer (a)

Why not others:
- the full three-day activity delay is partly absorbed by the A–D path's original two days of float

- delays of two, three, or four days do not match the change in the longest path

Key rule: A project delay equals the increase in the longest path, not necessarily the full delay of an activity on a noncritical path.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.