ITPEC IP April 2019 Question 56

Source exam: ITPEC IP April 2019Topic: Project Management

ITPEC IP April 2019 — Question 56 of 100

Project quality management defines and manages the procedures and performance measures needed to satisfy deliverable acceptance criteria. It plans quality standards, assures that suitable processes are followed, and controls results against the required level.

Answer (a)

Why not others:
- completing within budget is cost management

- identifying, analyzing, responding to, and monitoring uncertain events is risk management

- defining and controlling the work required for project success is scope management

Key rule: Quality management asks whether processes and deliverables meet requirements; cost, risk, and scope management address different project constraints.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.