ITPEC IP April 2021 Question 52
ITPEC IP April 2021 — Question 52 of 100
Defining project scope clarifies the work and activities that the project will implement. It establishes boundaries, deliverables, acceptance criteria, and included or excluded work so the team and stakeholders share a common baseline for planning and change control.
Answer (a)
Why not others:
- responding to a realized risk belongs to risk management
- handling schedule delay belongs to schedule control and corrective action
- high-level project objectives are normally established when the project is initiated, before detailed scope definition
Key rule: Scope definition answers what work and deliverables are included in the project.