ITPEC IP April 2018 Question 57
ITPEC IP April 2018 — Question 57 of 100
Defining project scope clarifies the work and activities that must be performed to produce the agreed deliverables. It establishes boundaries for what is included and excluded, providing a basis for the WBS, estimates, schedule, acceptance, and change control.
Answer (a)
Why not others:
- responding to a realized risk is part of risk management
- planning recovery from schedule delay is schedule control
- high-level project objectives are established during initiation and guide later scope definition
Key rule: Scope defines the required deliverables and work boundaries; objectives explain the intended result, while risk and delay responses are control activities.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.