ITPEC IP October 2021 Question 54
ITPEC IP October 2021 — Question 54 of 100
Project integration management creates the overall project management plan used to execute, monitor, and control the entire project. It coordinates the separate management areas and provides a unified basis for directing work and controlling changes.
Answer (d)
Why not others:
- the development schedule is primarily an output of schedule or time management
- the deliverables list belongs mainly to scope definition
- the project budget is produced through cost management
Key rule: Integration management combines and coordinates scope, schedule, cost, quality, resources, risks, and other plans into one coherent whole.