ITPEC IP October 2018 Question 97

Source exam: ITPEC IP October 2018Topic: System Planning

ITPEC IP October 2018 — Question 97 of 100

Acceptance inspection checks whether vendor deliverables conform to the requested specifications. The customer compares the delivered system, documents, and other outputs with contractual requirements and acceptance criteria before formally accepting completion.

Answer (b)

Why not others:
- reviewing an estimate occurs before placing an order

- asking for a proposed implementation is an RFP activity

- requesting preliminary vendor information is an RFI activity

Key rule: Procurement progresses from information and proposal requests to contracting, delivery, verification against acceptance criteria, and formal acceptance.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.