Creation of the computerization project belongs to the planning process. Planning establishes the business purpose, objectives, scope, feasibility, expected benefits, costs, risks, schedule outline, governance, and resources needed before detailed requirements and development begin.

Answer (c)

Why not others:
- operation runs and supports the delivered system

- development designs, builds, integrates, and tests the solution

- requirements definition specifies what the approved system must do

Key rule: Planning authorizes and frames the project; requirements and development elaborate and realize the system after that decision.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.