ITPEC IP April 2018 Question 58

Source exam: ITPEC IP April 2018Topic: Project Management

ITPEC IP April 2018 — Question 58 of 100

Defining team roles, responsibilities, required skills, and participation periods belongs to project human resource management. It determines how people will be organized, acquired, assigned, developed, and managed to perform the project work.

Answer (d)

Why not others:
- communication management plans the creation and distribution of project information

- scope management defines deliverables and required work

- time management develops and controls activities and the schedule

Key rule: Human resource management answers who will perform the work, with what authority and skills, and during which part of the project.

AI-generated — may contain errors