MRP calculates required component quantities based on a master production schedule and a Bill of Materials (BOM).

  • (b) ✓ — components are calculated from the standard production plan → this is exactly how MRP works
  • (a) — describes concurrent engineering (parallel development/design/production prep)
  • (c) — describes make-to-order / pull production, not MRP (MRP is plan-driven, not order-triggered)
  • (d) — describes kanban or shop floor control worksheets

Key rule: MRP = production plan + BOM → calculates what materials/components to order and when. It is a push-based planning system.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.