ITPEC FE Subject A April 2025 Question 40

Source exam: ITPEC FE Subject A April 2025Topic: Software Development

ITPEC FE Subject A April 2025 — Question 40 of 60

Sprint in Scrum — a fixed-length iteration for delivering a product increment.

A Sprint is a time-boxed period (typically 1–4 weeks) during which the Scrum team works to produce a potentially shippable product increment.

Why not others:
- (a) — describes the Daily Scrum (daily standup meeting)

- (c) — describes the Development Team role

- (d) — describes the Product Backlog

Key rule: Sprint = fixed time box + deliverable increment. Don't confuse with meetings, roles, or backlogs.