PDCA Cycle in SMS — Plan phase defines the framework of authorities, responsibilities, and process roles
ISO/IEC 20000-1:2011 applies the Plan-Do-Check-Act (PDCA) methodology to all parts of the Service Management System (SMS). The question asks which activity belongs to the Plan phase.
The correct answer is (b): Creating a framework of authorities, responsibilities, and process roles.
In the PDCA cycle applied to SMS:
- Plan: Establish the structure — define authorities, responsibilities, roles, and policies
- Do: Implement and operate — allocate funds, budgets, and resources
- Check: Monitor and review — conduct management reviews, maintain records
- Act: Improve — create and implement approved improvement plans
Why not the others:
- (a) Conducting management reviews and maintaining records → Check phase (monitoring and evaluation)
- (c) Creating a plan for approved improvements and reporting them → Act phase (continual improvement based on review findings)
- (d) Implementing and operating SMS through fund allocation → Do phase (execution and resource management)
Key rule: In PDCA for SMS, Plan = defining the "who does what" (governance framework), not creating improvement plans (which is Act) or allocating budgets (which is Do).
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.