ITPEC IP April 2026 Question 57
ITPEC IP April 2026 — Question 57 of 100
All four groups are stakeholders — each can affect the project or is affected by its outcome.
Company A's executives sponsor and govern the investment; its user department will use the system; Company B's project manager directs delivery; and the technical-support partner contributes work and depends on project decisions.
Answer (b)
Why not others: (a) omits the supplier project manager; (c) omits the customer's executives; (d) omits both executive sponsors and delivery management.
Key rule: Stakeholders extend beyond users and the core team to sponsors, suppliers, partners, and anyone with influence or impact.