ITPEC IP April 2025 Question 19

Source exam: ITPEC IP April 2025Topic: Software

ITPEC IP April 2025 — Question 19 of 100

50 minutes — add four daily incremental backups and Friday's full backup.

From Monday through Thursday, each backup copies 1,000 × 3 = 3,000 MB. At 10 MB/s, that takes 300 seconds, or 5 minutes per day, totaling 20 minutes. On Friday all 6,000 × 3 = 18,000 MB are copied, taking 1,800 seconds, or 30 minutes. The weekly total is 20 + 30 = 50 minutes.

Answer (c)

Why not others:
- (a) 25 counts five incremental backups and omits Friday's full backup

- (b) 35 adds just one incremental backup to the full backup

- (d) 150 misapplies the transfer rate or time conversion

Key rule: Calculate the data volume for each backup type, divide by throughput, convert units, and only then sum the scheduled runs.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.