A Pareto chart combines bars ordered from the largest category to the smallest with a cumulative-total line. It highlights the categories responsible for the greatest share of defects, complaints, or other outcomes. Teams can then prioritize improvement work on the few major causes before lower-frequency categories.
Answer (c)
Why not others:
- (a) Control chart plots process measurements over time against a center line and control limits
- (b) Tree diagram hierarchically decomposes a goal, cause, or subject into smaller elements
- (d) Matrix chart displays relationships among two or more groups of items
Key rule: Descending frequency bars plus a cumulative line uniquely identify a Pareto chart and support the vital-few prioritization principle.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.