ITPEC IP October 2024 Question 55
ITPEC IP October 2024 — Question 55 of 100
A Work Breakdown Structure, or WBS, decomposes the work required for a project into a hierarchical structure. Starting from major deliverables or phases, the team progressively divides the scope into smaller components and work packages that can be estimated, assigned, scheduled, monitored, and controlled. This also helps reveal omitted work.
Answer (d)
Why not others:
- (a) CMM is a maturity model for assessing and improving organizational software processes
- (b) ITIL is a body of guidance for IT service management
- (c) PERT is a project scheduling and estimation technique using a network of activities
Key rule: WBS answers what work is included; scheduling techniques such as PERT then help determine activity order and timing.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.