In the Act stage of PDCA, improvement measures are implemented for factors that prevented achievement of the target. After results have been measured and compared with the target, the organization corrects causes of poor performance and standardizes successful changes before beginning the next cycle.

Answer (d)

Why not others:
- defining the measurement method and target is Plan

- conducting the satisfaction survey according to the plan is Do

- analyzing the variance between measured and target values is Check

Key rule: PDCA means Plan the target and method, Do the work, Check results against the target, and Act to correct and improve.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.