ITPEC IP October 2018 Question 55
ITPEC IP October 2018 — Question 55 of 100
Quality planning should compare the benefits of quality activities with their required costs. Benefits can include less rework, greater productivity, fewer defects, and improved stakeholder satisfaction. This cost-benefit analysis helps select appropriate methods for achieving the target quality.
Answer (d)
Why not others:
- lessons and standards from similar past projects can be useful references
- review and testing should not be shortened automatically for schedule pressure
- quality must be balanced with scope, time, cost, and risk rather than given an unlimited budget
Key rule: Plan quality economically by choosing controls whose expected prevention and improvement benefits justify their cost.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.