ITPEC FE Subject A April 2024 Question 12

Source exam: ITPEC FE Subject A April 2024Topic: Computer Systems & Hardware

ITPEC FE Subject A April 2024 — Question 12 of 60

Capacity Planning Sequence — order work items when adding a new task to an existing monitored system.

Correct sequence: (iii) → (iv) → (ii) → (i)

  • (iii) Assess current system — review hardware performance from existing monitoring data
  • (iv) Gather requirements — meet users, understand the new task (process count, time needed)
  • (ii) Propose configuration — determine server count, parallel processing based on current state + new requirements
  • (i) Evaluate and review — assess whether the proposed configuration is appropriate

Why not others:
- (a) (iii),(ii),(iv),(i) — proposes configuration before gathering user requirements

- (c) (iv),(ii),(i),(iii) — gathers requirements before checking current system state

- (d) (iv),(iii),(i),(ii) — evaluates before proposing; puts requirements before current state assessment

Key rule: For an already-monitored system: Current state first → Requirements → Propose → Review.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.