The MRP process flows: Master Schedule → Gross Requirements → Net Requirements → Order Quantity → Arrangement Plan → Instructions.

Net requirements answer: "How much do we actually still need to order?" This is calculated as:
Net requirements = Gross requirements − Inventory on hand − Scheduled receipts

To perform this subtraction, you need to know the current inventory status — how much stock is already available, what orders are already incoming, and what is currently being processed.

Why not others:
- (a) Bill of materials feeds the gross requirements step (exploding the product structure to find total component needs), not the net calculation

- (c) Ordering policy (lot sizing, safety stock) is applied at the order quantity step — after net requirements are known

- (d) Standard schedule (lead time, completion period) is used at the arrangement plan step to determine timing of orders

Key rule: Net requirements = Gross − Inventory; therefore inventory status is the required input at that specific step.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.