ITPEC FE Morning April 2018 Question 71

Source exam: ITPEC FE Morning April 2018Topic: Management Strategy

ITPEC FE Morning April 2018 — Question 71 of 80

MRP Net Requirements Calculation — what input is needed to calculate net (shortage) requirements in MRP

MRP (Material Requirements Planning) follows a fixed sequence:

  1. Master schedule → what to produce and when
  2. Gross requirements → total materials needed (uses Bill of Materials)
  3. Net requirements → shortage after subtracting what's already available
  4. Order quantity → how much to order (uses ordering policy)
  5. Arrangement plan → when to order (uses lead time / standard schedule)
  6. Arrangement instructions → issue purchase/production orders

To calculate net requirements, the system subtracts existing inventory from gross requirements:

Net requirements = Gross requirements − (on-hand inventory + scheduled receipts + in-process quantity)

This means the input "A" must be inventory status — current stock levels, pending orders, and work-in-process quantities.

Why not others:
- a) Bill of materials — used earlier, at the gross requirements stage, to explode the product into its component parts

- c) Ordering policy — used later, at the order quantity stage, to determine lot sizes and ordering methods

- d) Standard schedule — used later, at the arrangement plan stage, to account for lead times and completion periods

Key rule: In MRP, "net" always means "gross minus what you already have" — so the input is always inventory status.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.