ITPEC FE Morning October 2021 Question 50
Topic: Software Development Management TechniquesAlso asked in April 2026
According to the Capability Maturity Model Integration, which of the following is the final and highest level of maturity?
Explanation
Optimizing — maturity level 5, the highest in CMMI.
The staged representation of CMMI has five maturity levels:
- Initial — processes are ad hoc; success depends on individuals
- Managed — projects are planned, monitored and controlled
- Defined — processes are standardized across the organization
- Quantitatively Managed — processes are measured and statistically controlled
- Optimizing — the measurements drive continuous process improvement
Answer (c)
Why not others:
- •(a) Auditable — not a CMMI maturity level; CMMI appraisals rate processes, but no level carries this name.
- •(b) Custom — not a CMMI maturity level either.
- •(d) Quantitatively Managed — level 4; processes are measured and controlled, but systematic improvement comes only at level 5.
Key rule: The CMMI levels climb from doing the work, to planning it, to standardizing it, to measuring it, and finally to improving it continuously.