ITPEC FE Morning October 2021 Question 50

According to the Capability Maturity Model Integration, which of the following is the final and highest level of maturity?

Explanation

Optimizing — maturity level 5, the highest in CMMI.

The staged representation of CMMI has five maturity levels:

  1. Initial — processes are ad hoc; success depends on individuals
  2. Managed — projects are planned, monitored and controlled
  3. Defined — processes are standardized across the organization
  4. Quantitatively Managed — processes are measured and statistically controlled
  5. Optimizing — the measurements drive continuous process improvement

Answer (c)

Why not others:

  • •(a) Auditable — not a CMMI maturity level; CMMI appraisals rate processes, but no level carries this name.
  • •(b) Custom — not a CMMI maturity level either.
  • •(d) Quantitatively Managed — level 4; processes are measured and controlled, but systematic improvement comes only at level 5.

Key rule: The CMMI levels climb from doing the work, to planning it, to standardizing it, to measuring it, and finally to improving it continuously.

Software Development Management Techniques · AI-written, may contain errors