Bathtub Curve — Early Failure Period — identify the correct countermeasure for the early failure phase.
The bathtub curve divides a system's life cycle into three failure periods:
- •Early failure period — high failure rate caused by design/manufacturing defects
- •Random failure period — low, constant failure rate during normal operation
- •Wear-out failure period — increasing failures due to aging and degradation
Countermeasures by period:
- Early → strengthen design review and failure analysis to eliminate defects before deployment
- Random → implement scheduled and condition-based maintenance
- Wear-out → perform preventive replacement or age-based maintenance
Why not others:
- (a) Prior replacement of components — addresses wear-out, not early defects
- (b) Scheduled and condition-based maintenance — addresses random failure period
- (c) Age-based maintenance on cumulative operating time — addresses wear-out period
Key rule: Early failures come from design flaws — fix the design process, not the hardware.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.