IPA IP 2021 Question 36
A question IPA Japan published in 令和3年度 ITパスポート試験 公開問題 問36, translated into English. ITPEC is based on the same exams.
Same question on ITPEC: Apr 2023 Q57
There is a project with a development period of 10 months and a labor cost budget for development of 10 million yen. After the elapse of five (5) months, the actual labor cost is recorded as 6 million yen, and 40% of the deliverables is complete. If the development is continued till completion with the same productivity, how much will the excess of the budget for labor cost be?
Explanation
5 million yen — at the same productivity the whole project will cost 15 million yen against a budget of 10 million yen.
Productivity here is how much deliverable each yen produces: 6 million yen of labour produced 40% of the deliverables.
- •Cost at completion: 6 ÷ 0.4 = 15 million yen
- •Excess over the budget: 15 − 10 = 5 million yen
The same in earned value terms: the work done is worth 10 × 0.4 = 4 million yen of budget but cost 6 million yen, so every yen of budgeted work costs 6 ÷ 4 = 1.5 yen, and 10 × 1.5 = 15 million yen. The elapsed 5 months do not enter the forecast.
Answer (d)
Why not others:
- •(a) 1 million yen — compares the 6 million yen spent with the 5 million yen planned for 5 months: an overrun so far, measured against time rather than work done, and not projected to completion
- •(b) 2 million yen — the overrun so far (6 million yen spent on work worth 4 million yen); the remaining 60% overruns at the same rate, adding another 3 million yen
- •(c) 2.5 million yen — would mean a total of 12.5 million yen, so the remaining 60% would cost 6.5 million yen, less than the 9 million yen that the observed rate gives
Key rule: Forecast the cost at completion as actual cost ÷ fraction complete (in EVM, budget ÷ CPI); the overrun so far understates the final overrun, which keeps growing with the remaining work.
Project Management · AI-written, may contain errors
This question comes from the past questions IPA Japan publishes, translated into English by ITPEC Practice. ITPEC Practice is an independent study tool and is not affiliated with IPA or ITPEC. See the original paper (PDF) or Report an issue.