Designate another office to assume headquarters functions and prioritize critical work — this directly enables business continuity after total loss.
A BCP specifies essential operations, alternate sites and authority, communications, resources, and tested procedures so priority services continue or recover within required time.
Answer (c)
Why not others: (a) is preventive fire safety but does not handle assumed total destruction; (b) waits for instructions from a headquarters that may be unavailable; (d) transfers financial loss and plans eventual relocation but does not provide immediate operational continuity.
Key rule: BCP focuses on continuing critical business under disruption, not only preventing damage or reimbursing losses.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.