ITPEC IP April 2025 Question 57
ITPEC IP April 2025 — Question 57 of 100
Estimate the added personnel expense and update the plan — this is the action specifically belonging to project cost management.
Adding members changes labor cost and may add onboarding or support expenses. Cost management estimates these effects, checks them against the budget and cost baseline, and updates the authorized plan through the project's control process.
Answer (d)
Why not others:
- (a) updating distribution lists is communications management
- (b) arranging training concerns resource development or procurement, though its cost may later enter the budget
- (c) assigning tasks and changing dates is primarily schedule and resource management
Key rule: Classify the management action by its direct object: money and budget are cost; information flow is communications; assignments are resources; dates are schedule.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.