ITPEC IP October 2024 Question 100
ITPEC IP October 2024 — Question 100 of 100
At minimum, the RFP must describe the functions the business information system is required to implement. A Request for Proposal tells candidate system integrators what business needs and requirements their proposed solution must satisfy. Without required functions, suppliers cannot define a relevant approach, estimate effort, or produce comparable proposals.
Answer (b)
Why not others:
- (a) the customer may state deadlines or constraints, but the detailed development schedule can be proposed by the SIer
- (c) the implementation method is a central part of the supplier's proposed solution
- (d) the supplier normally proposes the project team and its organization
Key rule: The RFP states the customer's needs and evaluation basis; each supplier's proposal explains how, when, and with whom it will meet them.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.