Only statement D is appropriate because production installation must follow an approved implementation plan. Adding a function to production can affect users, data, integrations, availability, and rollback. The change should therefore be planned, reviewed and approved before installation, with timing, verification, responsibilities, recovery steps, and communication defined.
Statements A, B, and C all improperly delay or omit planning and approval. A deadline does not justify installing without a plan. Creating the plan after installation cannot control the change that already occurred. In-house development also requires advance agreement because internal systems can still have significant operational impact.
Answer (d)
Why not others: (a), (b), and (c) each include at least one of the improper statements A, B, or C.
Key rule: Plan and authorize a production change before execution; document results afterward, and prepare rollback before it may be needed.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.