ITPEC IP April 2024 Question 47
ITPEC IP April 2024 — Question 47 of 100
The programmer receives the detailed design and performs the next development process: coding or programming. Software detailed design specifies module logic, interfaces, data structures, processing details, and other information needed to implement the program. The programmer translates that design into source code and normally performs associated unit-level verification.
Answer (d)
Why not others:
- (a) System auditor independently evaluates controls, compliance, and reliability rather than implementing the design
- (b) System operator runs and monitors the production system after deployment
- (c) System user uses the completed system and may participate in requirements or acceptance, but does not own the coding step
Key rule: In the basic development sequence, detailed design is followed by programming, then testing and later deployment or operation.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.