ITPEC IP October 2023 Question 55
ITPEC IP October 2023 — Question 55 of 100
A WBS, work breakdown structure, hierarchically decomposes project deliverables and the work needed to create them. Successive levels divide large deliverables into smaller components until manageable work packages can be estimated, assigned, scheduled, monitored, and controlled.
Answer (d)
Why not others:
- (a) EVM integrates scope, schedule, and cost measurements to evaluate project performance
- (b) RFP requests proposals from potential suppliers
- (c) SLA records agreed service content and service-level targets between provider and customer
Key rule: WBS decomposes what the project must deliver and the associated work; it provides a foundation for estimates and scheduling.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.