ITPEC IP October 2023 Question 53
ITPEC IP October 2023 — Question 53 of 100
The project manager creates and maintains the project management plan to guide execution, monitoring, control, and closure. It integrates subsidiary plans and baselines for scope, schedule, cost, quality, resources, communication, risk, procurement, and stakeholders. The plan explains how the project will be run and controlled.
Answer (c)
Why not others:
- (a) Request for proposal invites vendors to submit proposed solutions and terms
- (b) Project implementation report reports results or status rather than serving as the governing plan at launch
- (d) Requirements definition describes what the system must satisfy, not how the whole project is managed
Key rule: Requirements define the product; the project management plan defines how the work to produce it will be managed.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.