ITPEC IP April 2023 Question 52

Topic: Project ManagementAlso asked in November 2021

Among the measures A through C for risk treatment to be considered when a new product is developed, which of the following is the list that contains all and only appropriate measures for reducing quality-related risks?

A:Developing the product by using proven technologyB:Purchasing insurance against development delaysC:Creating a prototype of the product

Explanation

A and C — stable technology and a prototype both lower the chance of quality problems in the new product.

Risk treatment has four responses: avoid, reduce (mitigate), transfer and accept. Reducing a risk means lowering its probability or its impact.

  • •A — proven, stable technology has fewer unknown defects than new technology, so quality problems become less likely: reduction
  • •B — insurance against development delays passes the financial loss of a delay to the insurer: transfer, and of a schedule risk, not a quality risk
  • •C — a prototype lets users and developers find design flaws and misunderstood requirements early: reduction

Answer (b)

Why not others:

  • •(a) A, B — includes insurance, which does not reduce quality risk, and misses the prototype
  • •(c) A, B, C — includes insurance as well
  • •(d) B, C — includes insurance and misses stable technology

Key rule: Insurance transfers the financial effect of a risk and leaves its probability unchanged; reduction acts on the cause.