Build-to-order starts production after an order, so shipment takes time but excess finished-goods inventory is avoided. Actual demand triggers production, reducing dependence on forecasts and the risk of unsold products, although the customer must wait for manufacturing.

Answer (a)

Why not others:
- forecast accuracy and optimal finished-product inventory are central concerns of build-to-stock

- insufficient finished-product inventory is not the defining risk when production begins from actual orders

- producing to a forecast-based plan describes build-to-stock

Key rule: Build-to-order trades immediate shipment for low finished-goods inventory and lower overproduction risk.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.